What's New
-
Parking Structure B1 Construction Traffic: Trucks carrying construction materials will be accessing the Airport roadways, south of the terminal complex. Visitors to the Airport are encouraged to use extra caution when driving in this area...
-
Parking Structure B1: Removal of Parking Structure B1 is underway to make way for the new Terminal C...

Milestones
The Board of Supervisors recently:
-
Approved Terminal C and Parking Structure C construction bid documents;
Construction Progress:
-
A new security guard shack and fence is complete and operational at the Dove Street gate;
-
A new general aviation hangar has been completed in the area of Dove Street and Campus Drive;
-
A permanent construction access left-turn lane has been added northbound on Airport Way; (drivers should use caution in this area.)
Construction Status:
-
Parking Structure B1 closed permanently September 2nd and is being deconstructed to make way for Terminal C;
-
A portion of the South-Remain-Over-Night (RON) aircraft parking area is currently being utilized as a temporary vehicle parking lot. Construction is ongoing on the South RON project to install additional utilities and an extended fuel line that will be needed when the new Terminal C opens.