Timeline
The Airport Improvement Program is a multi-year program that includes the construction of new Terminal C, new Parking Structure C and updates to existing Terminals A and B with an estimated completion in late 2011.
Stage 1 (Complete)
- Build new South Remain-Over-Night (RON) aircraft parking area
- Stripe area for temporary passenger vehicle parking (Lot C)
![]() |
|||
|
|
Stage 2 (Complete)
- Open Parking Lot C and provide free shuttle service between parking area and the Riley Terminal
- Close and deconstruct Parking Structure B1
![]() |
|||
Stage 3 (Complete)
- Begin construction of new Terminal C including north and south commuter terminals
- Begin construction of new 2,000+ space Parking Structure C
- Begin construction of new Central Utility Plant
![]() |
|||
Stage 4
- Open new Terminal C (Complete)
- Open new Parking Structure C (Complete)
- Begin operation of new Central Utility Plant (Complete)
- Close Parking Lot C/Relocate aircraft to new South RON (Complete)
- Construct Phase 2 of Parking Structure C
![]() |
|||