Construction Stages and Timeline
The Airport Improvement Program is a multi-year program that includes the construction of new Terminal C, new Parking Structure C, a new Central Utility Plant, and updates to existing Terminals A and B with an estimated completion in late 2011.
Stage 1 (Complete)
- Build new South Remain-Over-Night (RON) aircraft parking area
- Stripe area for temporary passenger vehicle parking (Lot C)
Existing Facilities |
Under Construction |
Construction Complete |
Stage 2 (Complete)
- Open Parking Lot C and provide free shuttle service between parking area and the Riley Terminal
- Close and deconstruct Parking Structure B1
Existing Facilities |
Under Construction |
Construction Complete |
Stage 3
- Begin construction of new Terminal C
- Begin construction of new 2,000+ space Parking Structure C
- Begin construction of new north and south commuter/regional facilities
- Begin construction of new Central Utility Plant
Existing Facilities |
Under Construction |
Construction Complete |
Stage 4
- Open new Terminal C
- Open new Parking Structure C
- Begin operation of new Central Utility Plant
- Close Parking Lot C/Relocate aircraft to new South RON
- Construct Phase 2 of Parking Structure C (when needed)
Existing Facilities |
Under Construction |
Construction Complete |
The Airport Improvement Program includes construction of a new South Remain-Over-Night (RON) aircraft parking area, a new multi-level Terminal C with six new commercial passenger gates, new security checkpoints, new commuter facilities as well as new Parking Structure C and a Central Utility Plant.
Last updated: January 2011