John Wayne Airport anticipates issuing Requests for Proposals (RFPs) / Requests for Qualifications (RFQs) for the following Construction and A&E projects. Please note that this may not be a complete list of upcoming projects, and all dates are estimates and subject to change at any time.
Project Name:
Wireless Communication - 800 MHz
Project No.:
P209
Project Description:
Provide bi-directional antennas in pocket areas with no coverage.
Status:
In planning phase.
Upcoming Milestones:
Request for Proposals to be issued Summer 2012
Project Manager:
ARBELLA ARSENOUS (949) 252-5128 aarsenous@ocair.com
Maintenance Building
P206
Design/Build Project to construct a replacement maintenance building.
Pre-Qualification packages under JWA evaluation.
Request for Proposals to be issued Spring 2012
KORY HARIRI (949) 252-6098 khariri@ocair.com
Parking Access and Revenue Control System for Existing and New Parking Facilities (PARCS) (Design-Build)
P208/817
New Parking Revenue system which will include software and installation of some electrical and information technology equipment.
Parking Structures A1, A2, and B2 under construction as of March 2011
Issuance of Building Permit for PARCS at Parking Structure C
End of Construction Phase scheduled for November 04, 2011
Last Updated: April 6, 2012
The information above is subject to change at any time without notice and may not be all-inclusive.