Facts
Construction Stages
JWA’s Improvement Program is a multi-year program that includes the construction of a new Terminal C, two new parking structures and updates to existing Terminals A and B.
Stage 1
| 1. | Build new South Remain-Over-Night (RON) aircraft parking area | |
| 2. | Stripe area for temporary surface parking (Lot C) |
Existing Facilities |
Under Construction |
Construction Complete |
Stage 2
| 1. | Open Parking Lot C and provide free shuttle service between parking area and the Riley Terminal | |
| 2. | Close and deconstruct Parking Structure B1 |
Existing Facilities |
Under Construction |
Construction Complete |
Stage 3
| 1. | Begin construction of new Terminal C | |
| 2. | Construct new 2,000+ space Parking Structure C | |
| 3. | Construct new south commuter/regional facility |
Existing Facilities |
Under Construction |
Construction Complete |
Stage 4
| 1. | Open new Terminal C | |
| 2. | Open new Parking Structure C | |
| 3. | Close Parking Lot C / Relocate aircraft to new South RON | |
| 4. | Construct phase 2 of Parking Structure C and new north commuter/regional facility |
Existing Facilities |
Under Construction |
Construction Complete |
Program Schedule: