JWA’s Improvement Program is a multi-year program that includes the construction of a new Terminal C, two new parking structures and updates to existing Terminals A and B.

Stage 1
  1. Build new South Remain-Over-Night (RON) aircraft parking area
  2. Stripe area for temporary surface parking (Lot C)

Improvement Program Stage 1

blue background

Existing Facilities

taupe/white background

Under Construction

white background

Construction Complete

 

 
Stage 2
  1. Open Parking Lot C and provide free shuttle service between parking area and the Riley Terminal
  2. Close and deconstruct Parking Structure B1

Improvement Program Stage 2

blue background

Existing Facilities

taupe/white background

Under Construction

white background

Construction Complete

 

 
Stage 3
  1. Begin construction of new Terminal C
  2. Construct new 2,000+ space Parking Structure C
  3. Construct new south commuter/regional facility

Improvement Program Stage 3

blue background

Existing Facilities

taupe/white background

Under Construction

white background

Construction Complete

 

 
Stage 4
  1. Open new Terminal C
  2. Open new Parking Structure C
  3. Close Parking Lot C / Relocate aircraft to new South RON
  4. Construct phase 2 of Parking Structure C and new north commuter/regional facility

Improvement Program Stage 4

blue background

Existing Facilities

taupe/white background

Under Construction

white background

Construction Complete

 

 

 

Program Schedule:

Program Schedule

 